Installation of Trunk Water Mains in Lafayette St. – Project ID: MED595
Weekly Construction Bulletin
The following is the anticipated construction work schedule from Sat.-Fri.- 02-05-11 through 02-11-11
SATURDAY FEBRUARY 5, 2011 WORK HOURS: 8:00AM-4:30PM
LOCATION # 1: BROADWAY BETWEEN WASHINGTON ST. AND E. 4TH ST.
OPERATION: UTILITY RELOCATION
IMPACT: TRAFFIC WILL BE IMPACTED DUE TO LANE CLOSURES.
MONDAY THROUGH FRIDAY: WORK HOURS AT ALL LOCATIONS FROM 7:00AM- 3:30PM. (IF REQUIRED THE CONTRACTOR IS PERMITTED TO WORK UNTIL 6:00PM)
LOCATION # 1: INTERSECTION OF ASTOR PL. AND LAFAYETTE ST.
OPERATION: WATER MAIN PIER AND PLATE
IMPACT: TRAFFIC WILL BE IMPACTED DUE TO LANE CLOSURES.
LOCATION # 2: INTERSECTION OF GREAT JONES AND LAFAYETTE ST.
OPERATION: WATER MAIN PIER AND PLATE
IMPACT: TRAFFIC WILL BE IMPACTED DUE TO LANE CLOSURES.
LOCATION # 3: INTERSECTION OF BOWERY AND E. 4TH ST.
OPERATION: EXCAVATION FOR THE 24” ROUND ABOUT CATCH BASIN INSTALLATION
IMPACT: TRAFFIC WILL BE IMPACTED DUE TO STREET CLOSURES.
E. 4TH ST BETWEEN BOWERY AND LAFAYETTE ST. WILL BE CLOSED ON A DAILY BASIS MONDAY – FRIDAY 7:00AM – 3:30PM (SOME DAYS UNTIL 5:30PM). THESE CLOSURES ARE NECESSARY TO ADDRESS IMMEDIATE CONSTRUCTION CONCERNS. THE STREET WILL BE REOPENED AT THE END OF EACH WORKING DAY
LOCATION # 4: INTERSECTION OF E. 4TH ST. AND BROADWAY
OPERATION: UTILITY RELOCATION
IMPACT: TRAFFIC WILL BE IMPACTED DUE TO LANE CLOSURES.
For further information please contact the Community Construction Liaison Karen Flores at 212-228-0731. For more information please visit: www.nyc.gov/buildnyc.